The INPS has rejected the requests for 13 weeks of redundancy fund for 300 workers of Seli Overseas, a company owned by Webuild. #TerzoValico #CassaIntegrazione #Lavoro (translated)

The INPS has rejected the requests for 13 weeks of redundancy fund for 300 workers of Seli Overseas, a company owned by Webuild. #TerzoValico #CassaIntegrazione #Lavoro (translated)

The Third Valico is slowing down due to construction sites being halted and a lack of funds, provoking the anger of the 340 workers who are warning of the risk of a social bomb. #TerzoValico #Lavoro #Ferrovia (translated)

At the Third Valico construction sites, over 50 workers have been transferred and six new employees are on layoffs due to the suspension of work for an economic dispute, while the unions are waiting for a meeting with Cociv to discuss a possible resumption of activities. #TerzoValico #CassaIntegrazione #Lavoro (translated)

Despite the allocation of an additional 2.45 billion euros for the Third Valico until 2030, 336 workers remain on unemployment benefits and 16 have been laid off, while the situation at the construction sites of Radimero and Val Lemme continues to be critical. #TerzoValico #CassaIntegrazione #Lavoro (translated)

The Minister of Infrastructure and Transport Matteo Salvini confirmed that the funds for the Third Valico Milan-Genoa are available and reiterated the importance of completing the work, currently at 97.6%, to avoid halting progress on construction sites in the region. #TerzoValico #Logistica #Infrastrutture (translated)

In the construction sites of the Third Pass between Liguria and Piedmont, the collective dismissal of 16 workers from Gallerie has begun, in a context of economic difficulties and suspension of work due to disputes between the companies involved. #TerzoValico #Lavoro #Infrastrutture (translated)

Rfi has ordered the resumption of work for the Third Valico, but Cociv warns that the funds are exhausted, leading to a possible total halt of the project. #TerzoValico #Alessandria #Infrastrutture (translated)

The Third Lot is at risk of being halted, with 1,800 jobs threatened due to a lack of funds amounting to between 2.1 and 3 billion euros. #TerzoValico #Alessandria #sindacati (translated)

The Third Crossing project is facing difficulties, with redundancy benefits activated for 300 workers due to slowdowns in the work, also threatening future high-speed rail and potentially involving 1,800 workers in Piedmont and Liguria. #TerzoValico #CassaIntegrazione #Lavoro (translated)

The unions warn of the risk of a possible halt to the construction sites of the Third Pass due to the request for an additional 3 billion by Webuild, which could endanger the jobs of 1,800 workers. #TerzoValico #Webuild #Sindacati (translated)