Christian Sandström wrote that Stegra's half-year report to the Energy Agency for January–June 2026 described delays and financing problems, and that an appendix stated that construction production had progressed more slowly than planned, the timeline was being reviewed, and new funding would cover higher project costs. At the same time, the company stated, according to Sandström, that financing was secured and responded yes to the question of whether the project was proceeding as planned. Sandström stated that the report was dated September 2 and that less than a month later, headlines once again reported that Stegra needed to raise at least ten billion kronor more. He suggested that those who relied on the company's communications had only themselves to blame and referred to AFV Magasin for more information. https://t.co/ouqqVBnFM4 #Stegra #kostnader #finansiering (translated)